What shipped, what's next and what could go wrong — written by the person doing the work, not a project manager.
Week of Oct 5
MX
MaxPrincipal · Fri, Oct 9
On track
Purchase orders are working end to end on staging — draft, send, partial receive, close. Receiving is the last big flow and is waiting on the v3 designs.
Shipped
PO lifecycle on staging (draft → sent → partial → received)
Supplier lead-time tracking with late flags
3PL webhooks live in production behind a flag (CO-01)
Next
Receiving build starts Oct 19, after design sign-off
Release candidate 2 on staging, Oct 23
Forecast: wire in seasonality from 2025 orders
Risks
CO-02 (wholesale) needs a decision by Oct 16 to hold the Nov 20 launch, or it moves to Nov 27.
Week of Sep 28
PS
Priya ShahSenior engineer · Fri, Oct 2
On track
Lots and traceability are in. Every unit can now be traced from supplier lot to customer order in two clicks.
Shipped
Lot tracking with expiry and CoA attachments
Ridgeline 3PL webhooks (CO-01) on staging
Recall search across orders by lot
Next
PO lifecycle end to end
Receiving designs v3 from Theo
Load-test the NetSuite sync at 3× volume
Risks
None this week.
Week of Sep 21
MX
MaxPrincipal · Fri, Sep 25
On track
Shopify and NetSuite are syncing both ways. Inventory overview is live on staging for your team to poke at.
Shipped
Two-way Shopify ↔ NetSuite sync
Inventory overview + SKU drawer on staging
Staging logins for Dana, Rafi and Jules
Next
Lots + traceability
Start 3PL webhooks (CO-01)
Risks
None this week.
Week of Sep 14
PS
Priya ShahSenior engineer · Fri, Sep 18
On track
Data model is locked and migrations are running nightly against a copy of production.