Weekly updates

Every Friday, in writing.

What shipped, what's next and what could go wrong — written by the person doing the work, not a project manager.

Week of Oct 5
MX
Max Principal · Fri, Oct 9
Ops platform On track

Purchase orders are working end to end on staging — draft, send, partial receive, close. Receiving is the last big flow and is waiting on the v3 designs.

Shipped

  • PO lifecycle on staging (draft → sent → partial → received)
  • Supplier lead-time tracking with late flags
  • 3PL webhooks live in production behind a flag (CO-01)

Next

  • Receiving build starts Oct 19, after design sign-off
  • Release candidate 2 on staging, Oct 23
  • Forecast: wire in seasonality from 2025 orders

Risks

  • CO-02 (wholesale) needs a decision by Oct 16 to hold the Nov 20 launch, or it moves to Nov 27.
SO
Sam Okafor Data · Fri, Oct 9

Churn model v10.2 is trained and beats v10.1 on every segment. We can ship Oct 15 — but it is learning from subscription data that is now 9 days stale.

Shipped

  • Churn v10.2 trained — AUC 0.84 → 0.87
  • Reorder forecast recalibrated for Q4
  • Winback segment synced to Klaviyo

Next

  • Release sign-off from Dana (Oct 14)
  • Ship v10.2 to the dashboard (Oct 15)
  • Monthly insights review (Oct 20)

Risks

  • Recharge export access still pending with Verdant IT — ticket #4471. Without it, v10.2 ships on Oct 3 data.
Week of Sep 28
PS
Priya Shah Senior engineer · Fri, Oct 2
Ops platform On track

Lots and traceability are in. Every unit can now be traced from supplier lot to customer order in two clicks.

Shipped

  • Lot tracking with expiry and CoA attachments
  • Ridgeline 3PL webhooks (CO-01) on staging
  • Recall search across orders by lot

Next

  • PO lifecycle end to end
  • Receiving designs v3 from Theo
  • Load-test the NetSuite sync at 3× volume

Risks

None this week.

Week of Sep 21
MX
Max Principal · Fri, Sep 25
Ops platform On track

Shopify and NetSuite are syncing both ways. Inventory overview is live on staging for your team to poke at.

Shipped

  • Two-way Shopify ↔ NetSuite sync
  • Inventory overview + SKU drawer on staging
  • Staging logins for Dana, Rafi and Jules

Next

  • Lots + traceability
  • Start 3PL webhooks (CO-01)

Risks

None this week.

SO
Sam Okafor Data · Fri, Sep 25

September cycle closed. The reorder forecast caught the Magnesium stock-out risk 19 days early.

Shipped

  • September insights review
  • Cohort retention tile now splits by acquisition channel
  • Anomaly alerts routed to #ops-alerts

Next

  • October cycle planning (Oct 1)
  • Churn model retrain with skip-frequency features

Risks

None this week.

Week of Sep 14
PS
Priya Shah Senior engineer · Fri, Sep 18
Ops platform On track

Data model is locked and migrations are running nightly against a copy of production.

Shipped

  • Ops data model v1 locked
  • Nightly migration rehearsal against prod copy
  • SKU master cleaned — 41 SKUs, 0 duplicates

Next

  • Shopify ↔ NetSuite sync
  • Inventory overview UI

Risks

None this week.

Week of May 25
MX
Max Principal · Fri, May 29

Handoff complete. Your team owns the store now — docs, recordings and a 30-day support window are in Files.

Shipped

  • Two recorded training sessions
  • Theme + Recharge runbooks
  • Post-launch report: checkout p95 3.9s → 1.2s

Next

  • 30-day support window (ends Jun 28)

Risks

None this week.